The scope of works consisted of the design and construction of 2 breakwaters of 1,100 m & 600 m long to create a harbour basin of about 360,000 m² which had to be dredged to –10m (partly to –6m). The dredged material was used as reclamation material to raise the level of the onshore harbour platform by about 2m.
Project name
Fujairah Naval Base Breakwaters
Area(s) of expertise
Breakwaters
Location
Fujairah, United Arab Emirates
Stakeholder(s)
Six Construct
Client
UAE Armed Forces General Directorate of Military Armies UAE
Building Period
2001 - 2004
Total value
$ 23.9 million